SpaceX appears to be making great progress towards the start of its first full Super Heavy static fire campaign, building upon extensive Starship testing and a single booster static fire completed in July 2021.
On May 14th, upgraded Super Heavy booster B7 was moved back to SpaceX’s South Texas Starbase Starship factory after completing a successful round of tests and smoothing out an otherwise rocky start to its life. It was not the booster’s first time on that journey: after first leaving the Starbase ‘nest’ on March 31st, Booster 7 suffered significant internal damage during a structural stress test on April 14th and was forced to return to the factory for repairs. Impressively, despite the cramped environment and extremely limited access to the interior of the Super Heavy’s primary and secondary propellant tanks, SpaceX engineers and technicians somehow completed those repairs and Booster 7 sailed through a new round of ‘cryoproof’ testing on May 9th and 11th.
In the ~20 days since its second return, SpaceX teams have been hard at work preparing Super Heavy B7 for its next major challenges – the results of which could determine whether the massive rocket helps launch a Starship into space later this year.
That goal, same as it has been for half a year, is to qualify the first Super Heavy booster for flight. To do so, SpaceX must – at long last – static fire a Super Heavy with all necessary Raptor engines installed. For Booster 7 and its near-term successors, that means 33 new “Raptor 2” engines capable of generating a total of ~7600 metric tons (~16.7M lbf) of thrust.
That’s exactly what SpaceX workers have been focused on doing since Booster 7’s second return to a Starbase assembly bay. Bit by bit, they have spent every day since installing Raptor 2 engines one at a time. Unfortunately, due to the Super Heavy’s relocation inside a brand new assembly building known as the Megabay, High Bay 2, or Wide Bay, the half-dozen or so unaffiliated photographers who have come to regularly photograph Starbase have yet to find an angle that shows the state of that engine installation progress.
Two weeks later, it’s clear that SpaceX is taking its time, which likely also implies that the company is simultaneously encasing Booster 7’s Raptors and engine section in shrouds that will protect them during static fire testing; as well as during launch, reentry, and landing if B7 makes it that far. That’s not guaranteed, however, and it could also simply be that installing 33 engines on the first attempt at installing any Raptor 2s on any rocket has proven much harder than expected.
On June 1st, CEO Elon Musk appeared to confirm that engines are still being installed on Super Heavy B7, but he also verified that “all Raptor 2 engines needed for [the] first orbital flight are complete.” That could include Starship S24, which needs three sea-level Raptor 2s and three vacuum-optimized Raptor 2s, but it’s still great news even if he only means it for Booster 7. SpaceX has been spotted delivering at least a handful of new Raptor 2 engines a week for the last month or two, which means that all 33 engines may already be onsite at Starbase. If some are still undergoing proof testing at SpaceX’s McGregor, Texas facilities, it could be a few more weeks before all necessary engines are onsite, but that milestone is likely close at hand if it hasn’t already been reached.